| |
Projects Under ConstructionRoripaugh Ranch Fire Station
The majority of work was completed by April of 2006. The remaining work will be completed when the mainline utilities are installed, which the City is undertaking - estimated start in March of 2010. A fire engine/truck venting system (requested/added on 2/06) will be installed when the Contractor re-mobilizes, this cost is also included in the approved change order total. Temporary power, initially established in 2003 by the developer, had to re-established in May of 2010.
|
City Property at Diaz Road and Dendy Parkway (Northwest RDA Property) - Rough Grading
This project provided for the rough grading of the vacant City property at Diaz Road and Dendy Parkway. All work was completed on March 28, 2007. Site restoration, including hydroseeding, was completed in December of 2008. A notice of completion was approved by the City Council at the 1/13/09 meeting. Ongoing maintenance expenses will be incurred for NPDES measures until such time the property is developed. Minor BMP improvements were completed in April of 2010.
|
Old Town Infrastructure Project -Town Square and Mercedes & Main Street
This project involves construction of the Town Square and street improvements on Mercedes & Main Streets. The project was awarded on March 18, 2008. Various specialty items and added work extended the completion date through Spring of 2010. In addition final paving in this contract will be deferred to the completion of the Civic Center.
|
Pechanga Parkway Phase II Street Improvements from Temecula Parkway to City Limits @ Pechanga Rd.
This project widens Pechanga Pkwy to its ultimate width from Temecula Pkwy to Pechanga Rd. The contractor has completed the improvements. The EMWD claim against AAA has been settled. Final steps are being taken to close out this claim which in turn will closeout this project.
|
Old Town Infrastructure Projects
- Parking Structure & Office/Retail Frontage
The structure was opened to the public on March 1, 2010. Punch list and close out work will be ongoing for two to three months. In addition a long term (5 year) maintenance contract will be established for enhanced landscaping constructed in the Caltrans right of way as part of this project (authorization to bid on 7/13/10).
|
Ronald Reagan Sports Park Channel Silt Removal & Desiltation Pond
This project includes restoring the Best Management Practices (BMP) of the Stormwater Pollution Prevention Plan (SWPPP), the Water Quality Management Plan (WQMP) and the requirements of RWQCB by desilting the basin located near the Sports Park. 401 Certification, Streambed Alteration Agreement, and Nationwide Permits have been acquired. Contract with current contractor is in the process of being closed out.
|
Old Town Civic Center
This project will construct the Old Town Civic Center. City Council awarded the contract to Edge Development, Inc. on 09/09/08. Edge began work on 4/8/09. Work is ongoing on interior drywall, painting, tile work, drop ceilings, casework and detail work for mechanical, electrical and plumbing. Carpet install starting 7/26 and systems furniture on 8/2/10.
|
Temecula Community Center Expansion - Phase 2, Renovation of Historical Buildings
Phase 2 of this project will renovate the Escallier House and Barn. Bids were opened on March 4, 2010. A recommendation to award a contract was approved at the City Council at the 03/23/10 meeting. Notice to proceed is effective 05/03/10 for Phase 2. Grade beams are complete. Utilities, rough in of plumbing and electrical is in process.
|
Redhawk Park Improvements
This project will add amenities, which include ADA accessible parking, a restroom, a half-court basketball court, and permanent dog park at Redhawk Community Park. As part of this project, a seatwall will be installed at Sunset Park. The Notice To Proceed was issued 12/21/09. Construction activities began in January 2010. Completion is anticipated in October 2010.
|
Pavement Rehabilitation Rancho California Road (Ynez to East City Limit) - STPL Project
This project will rehabilitate Rancho California Road from Ynez Road to the City limits on the east. Construction began on June 3, 2009. The contractor is just about done with punchlist items.
|
Winchester Road / State Route 79 North - North Corridor Beautification
This federally funded project will design and construct landscaping and irrigation enhancements to the existing raised medians along Winchester Road between Ynez Road and the easterly City limits. The contractor is currently working on phases 1, 2 & 3 in the existing medians installing the irrigation systems and constructing the monument walls.
|
Citywide Slurry Seal Project FY 2009-2010
This project will slurry seal local streets within the Roripaugh Hills Estates, Campus Verdes and Nicholas Valley Areas. Proposition 1B funds will be used to fund this project. A Pre-Con is set for July 15, 2010.
|
Road and Storm Drain Repair at Rancho California Road
Storm drain pipes have been determined to be essentially sound. The approach from this point will take the form of debris removal, surface preparation, and installation of concrete paving in the pipe invert to extend the life of the pipe; no roadway repair is anticipated. Construction contract awarded at the 6/22/10 Council meeting; pre-construction meeting to be held week of 7/12/10.
|
Citywide Storm Drain Improvements - Rancho California Rd at Vincent Moraga Dr
Project consists of installing two catch basins and approx. 100' of RCP drainage pipe across Rancho California Road at Vincent Moraga Drive, as well as relocation of an existing RCWD waterline. Bid opening was held 6/29/10, ATOM Engineering is apparent low bidder. Contract award scheduled for the 7/13/10 Council meeting, pre-construction meeting to be held shortly.
|
Road Reconstruction at Jedediah Smith Road
Project will rehabilitate roadway surface using the Asphalt Rubberized Aggregate Membrane (ARAM) method on Jedediah Smith Road between Temecula Parkway and Cabrillo Ave; on Cabrillo Ave between Jedediah Smith Road and Vallejo Ave; and on Vallejo Ave between Cabrillo Ave and Ynez Road. Bid opening was held on 5/17/10, contract awarded to ICE Engineering at the 6/8/10 Council meeting. Pre-construction meeting held 6/24/10, construction anticipated to begin the week of 7/19/10.
|
Citywide Concrete Repairs FY 2009-2010
This project will consist of various concrete repairs throughout the City. A Pre-Con is currently being scheduled.
|
Projects Being Advertised for BidsCitywide Slurry Seal Project FY 2009-2010
This Project is the annual slurry seal project that will slurry seal local streets within the City. Bid opening is scheduled for July 26, 2010.
|
Closed Circuit Television (CCTV) Installation on Temecula Parkway
This Project will install fiber optic cable in existing conduits and 4 television cameras at four intersections to monitor traffic flow on Temecula Parkway between Pechanga Parkway and Butterfield Stage Road. Bid opening is scheduled for July 20, 2010.
|
Projects Being Designed By ConsultantsRe-Stripe Route 79 South to 8 lanes from Pechanga Parkway to I-15
This project will provide four lanes in each direction on Temecula Parkway (formerly State Route 79 South) from I-15 to Pechanga Parkway. This project is on hold until the I-15 / SR-79S Ultimate Interchange, Project No. PW04-08 is complete.
|
Pechanga Parkway Storm Drain Improvements - Environmental Mitigation
This project includes construction of new wetlands for the Wolf Valley Creek Channel Improvements-Stage I. The wetlands will be created through construction of new landscape/irrigation systems. The site is located along the north bank of Temecula Creek (within flood-plain/way areas). The environmental regulatory agencies have approved this new mitigation area. Mylars are ready for signature. A site visit with the DFG took place on 03/16/10. Another site visit, this time with Army Corps and Regional Water Board was conducted on April 23rd. Water table level tests showed no sign of water within 18' depth. Resource agencies are being consulted as to the next step.
|
Murrieta Creek Bridge and Overland Drive Extension from Commerce Center to Diaz Rd
The project includes the extension of Overland Drive from Commerce Center Drive to Diaz Road with a bridge over Murrieta Creek. Coordination with RCFC & WCD, U.S. Army Corps of Engineers and the state environmental regulatory agencies is required. the design is complete and the City has the mylars and the electronic files of the plans.
|
Main Street Bridge Over Murrieta Creek (Replacement)
This project will replace the existing Main Street Bridge over Murrieta Creek. Design consultant Simon Wong Engineering (SWE) and the City are continuing to pursue environmental permitting and coordination issues associated with pursuing the bridge replacement as a project separate from the Army Corps of Engineer's Murrieta Creek Improvement project. Environmental technical reports required for NEPA clearance were resubmitted to Caltrans on 4/15/10; response on cultural reports was received on 5/27/10, biology comments received and forwarded to consultant on 6/23/10. Revised technical reports anticipated from consultant the week of 7/12/10, resubmittal to Caltrans for final review to follow.
|
Pedestrian/Bicycle Bridge Over Santa Gertrudis Creek
This project includes the construction of an approx. 150' long ped/bike bridge over Santa Gertrudis Creek near Chaparral H.S. This is a federally funded project, which will involve a NEPA document. Environmental clearance (Categorical Exclusion) was obtained from Caltrans on 5/20/10. Request for Authorization (RFA) to Proceed with Construction package submitted to Caltrans on 06/24/10, approval anticipated by end July/mid-August.
|
Western Bypass Bridge Over Murrieta Creek
This project involves the design, environmental clearance, and construction of a new bridge over Murrieta Creek at the westerly terminus of Western Bypass and an extension of Pujol Street to the new structure. Once constructed, this will serve as the southerly connection of the Western Bypass Corridor. 100% Plans and Specs are being reviewed. The Mitigated Negative Declaration was adopted. Applications to the various environmental agencies have been submitted.
|
Temecula Park and Ride (79 South)
This project will design and construct a park and ride facility on Temecula Parkway (formerly 79 South) at La Paz. The consultant is working to finalize the plans. 100% submittal is expected during the next period.
|
Pechanga Pkwy-Dual Right Turn Lanes from
Temecula Parkway (SR 79S)
This project included the design and construction of 2 right-turn lanes on eastbound Temecula Pkwy to southbound Pechanga Pkwy. The Pechanga Pkwy Ph II Street Improvements' contractor has completed this work, as a change order to their contract.
|
French Valley Parkway / Interstate 15 Over-Crossing and Interchange Improvements - Phase 1 (PS&E)
A southbound off-Ramp to Jefferson, an auxiliary lane, and widening the bridge over Santa Gertrudis Creek at the Winchester southbound off-ramp are the components of Phase 1. City continued the design work. Status is as follows:
> 95% PS&E - Being prepared for submittal to Caltrans July 2010.
> Right of Way - Establishing limits of dedication.
> Declaration of Units - Caltrans Approved Metric Exception for this phase.
> Utilities - Pothole of existing utilities within APE are complete. Relocation Claim Letter was sent to all utility companies.
|
Old Town Gymnasium
This projects involves the design of the approximately 9,000 square foot gymnasium adjacent the Boys & Girls Club on Pujol Street. The land is to be utilized as staging area for the Murrieta Creek Improvements project and it will need to be acquired from Riverside County Flood Control (RCFC) for the current design. A time line was established by TCSD for the design and environmental work. The TCSD Board of Directors approved the Conceptual Master Plan on May 11, 2010. Consultant has begun design and environmental work.
|
Santa Gertrudis Creek Pedestrian/Bicycle Trail Extension and Interconnect
The project will provide a Class I bicycle trail that connects the existing Santa Gertrudis Creek Pedestrian/Bicycle Trail at Ynez Road to the Murrieta Creek Multi-Purpose Trail at Diaz Road. The City Council approved an agreement with Hall & Foreman at the 11/25/08 meeting. The kick off meeting was held on 01/08/09. The alignment study has been completed. Extension of time for the Bicycle Transportation Account funds was approved on 05/01/09. The consultant is working on 90% plans, specifications and estimate.
|
Nicolas Valley - Assessment District (Liefer Road)
This project will study assessment district feasibility and formation, including completing the street and minor storm drain improvements on the unimproved portions of certain streets within Nicolas Valley (Liefer Road) area. Consultant is finalizing 100% plans for signature.
|
Roripaugh Ranch Street Improvements - Phase I
Ph I includes the design & construction of Butterfield Stage Road (BSR) from Murrieta Hot Springs Road (MHSR) to Calle Chapos, a portion of MHSR, Calle Chapos, South Loop Rd and making the Fire Station functional. David Evans and Associates' (DEA) and Hirsh & Associates, Inc. (HAI) were awarded contracts to complete the design. Final (100%) plans were returned to DEA for corrections. Staff is working on the Bid Docs. The City Attorney is to review the impacts of the FDIC's new involvement.
|
Traffic Signal Installation - Citywide
This project will install traffic signals at two intersections; Meadows Parkway at Pauba Road and Rancho California Road at Yukon Road. Completion of Plans and Specifications is anticipated in July 2010. Consultant is finalizing 100% plans for signature.
|
I-15 / SR-79S Ultimate Interchange
30% PS&E - Comments received from Caltrans on 05/20/10. Revisions are being prepared.
60% PS&E - Submittal to Caltrans scheduled for August 2010.
|
Projects in the Planning StageFrench Valley Parkway / Interstate 15 Over-Crossing and Interchange Improvements (PA & ED)
Project Report - Approved January 2010.
Environmental Document - Approved January 2010.
New Connection Report - Approved April 2010.
Freeway Agreements - City Council to evaluate for signature 07/13/2010.
|