| |
Projects Under ConstructionRoripaugh Ranch Fire Station
The majority of work was completed by April of 2006. The remaining work will be completed when the mainline utilities are installed, which the City is undertaking - estimated start in December of 2011. A fire engine/truck venting system (requested/added on 2/06) will be installed when the Contractor re-mobilizes, this cost is also included in the approved change order total. Temporary power, initially established in 2003 by the developer, had to re-established in May of 2010.
|
Old Town Infrastructure Project -Town Square and Mercedes & Main Street
This project involves construction of the Town Square and street improvements on Mercedes & Main Streets. The project was awarded on March 18, 2008. Final work items involve completion of the show power which is in design and set to be constructed in Fall 2011.
|
Old Town Civic Center
This project will construct the Old Town Civic Center. City Council awarded the contract to Edge Development, Inc. on 09/09/08. Edge began work on 4/8/09. Dedication ceremony was held on 12/9/10 and the City started operations from the new structure on 12/20/2010. Resolution of punchlist and added work items are ongoing.
|
Pedestrian/Bicycle Bridge Over Santa Gertrudis Creek
This project includes the construction of an approx. 150' long ped/bike bridge over Santa Gertrudis Creek near Chaparral H.S. Bids were opened August 16, 2011 - Bowcon Company is the apparent low bidder. Contract was awarded at the 9/13/11 City Council meeting. Pre-construction meeting to be held on 9/21/11.
|
Winchester Road / State Route 79 North - North Corridor Beautification
This federally funded project will design and construct landscaping and irrigation enhancements to the existing raised medians along Winchester Road between Ynez Road and the easterly City limits. The City hired a contractor recommended by the bonding company to replace the dead and missing plants. The planting started during the week of September 12th.
|
Ronald Reagan Sports Park Desilting Basin Environmental Mitigation
This project involves the installation of landscape and irrigation improvements on a .26 acre Habitat Creation Area and maintaining it for five (5) years in accordance with a Habitat Mitigation and Monitoring Program. The work was completed on 1/20/11. The project is now in the 5-year maintenance/monitoring program. Coordination efforts with the Regional Conservation Authority (RCA) to establish a conservation easement on the 0.26 acre parcel, in accordance with the requirements of the DFG permit, have been concluded. Dedication of the easement to be presented to the City Council at the 9/27/11 meeting.
|
Margarita Road Right-of-Way Enhancement
This project will enhance the east side of Margarita Road parkway from Ramsey Court to Avenida Cima Del Sol. A contract was awarded to KASA Construction at the 07/26/11 City Council meeting. The pre-construction meeting was held on 8/24/11 and a Notice to Proceed was issued for 9/12/11 start date. The Contractor has mobilized and construction is scheduled for completion by the end of November 2011.
|
Citywide Concrete Repairs - FY2010-11
This project is an annual maintenance project. The project involves removing and replacing various damaged concrete facilities throughout the city. The contractor has begun work and completion is anticipated by the end of October.
|
Pavement Rehabilitation Program - Margarita Road Project 1
This project will rehabilitate Margarita Road between Rancho California Road and Avenida Barca. Construction contract was awarded at the 7/26/11 City Council meeting. The pre-construction meeting was held on 8/8/2011. Construction is to begin in mid-September.
|
Pavement Rehabilitation Program - Winchester Road
This project will rehabilitate Winchester Road between Roripaugh Road and Nicolas Road. The Notice to Proceed was issued to the contractor to start on September 19, 2011.
|
Projects Being Advertised for BidsRoripaugh Ranch Street Improvements - Phase I
Phase I improvements involve wet and dry utilities, sidewalks, medians and new roadway section on Butterfield Stage Road (BSR) from Murrieta Hot Springs Road (MHSR) to Calle Chapos, a portion of MHSR, Calle Chapos, South Loop Road. The project will also utilities to the Fire Station and future amenities (e.g, traffic signals, park, ..etc.). The project is being advertised for construction bids. Bid opening is scheduled for 09/20/11.
|
Projects Being Designed By ConsultantsPechanga Parkway Storm Drain Improvements - Environmental Mitigation
This project includes construction of new wetlands for the Wolf Valley Creek Channel Improvements-Stage I. Site visits for a new proposed location was conducted with the Department of Fish&Game (DFG) and Regional Water Board in May. City will contract with a consultant to map the new proposed area and obtain resource agencies approval.
|
Murrieta Creek Bridge and Overland Drive Extension from Commerce Center to Diaz Rd
The project includes the extension of Overland Drive from Commerce Center Drive to Diaz Road with a bridge over Murrieta Creek. The design is complete and the City has the mylars.
|
Main Street Bridge Over Murrieta Creek (Replacement)
This project will replace the existing Main Street Bridge over Murrieta Creek. All resource agency permits have been acquired, with the Army Corps of Engineers (ACOE) 404 permit having been obtained on 8/16/11. Riverside County Flood Control District encroachment permit application is currently being processed, and once this permit is issued, the Request for Authorization (RFA) to construct will be submitted to Caltrans.
|
Western Bypass Bridge Over Murrieta Creek
This project involves the design, environmental clearance, and construction of a new bridge over Murrieta Creek at the westerly terminus of Western Bypass and an extension of Pujol Street to the new structure. Once constructed, this will serve as the southerly connection of the Western Bypass Corridor. The Mitigated Negative Declaration was adopted. Applications to the various environmental agencies have been submitted. Review of the 100% Plans and Specs is on-going.
|
Temecula Park and Ride (79 South)
This project will design and construct a park and ride facility on Temecula Parkway (formerly 79 South) at La Paz. The City just received the 100% plans and all reports. The design is complete. This project will be shelved until construction funds are identified.
|
French Valley Parkway / Interstate 15 Over-Crossing and Interchange Improvements - Phase 1 (PS&E)
A southbound off-Ramp to Jefferson, an auxiliary lane, and widening the bridge over Santa Gertrudis Creek at the Winchester southbound off-ramp are the components of Phase 1. City continued the design work. Status is as follows:
> Final PS&E - City/Caltrans coordinating final revisions.
> Right of Way - R/W Appraisal Map under Caltrans review.
> Utilities - Utility Agreements for SCE, Verizon & EMWD expected to be authorized at 09/27/2011 City Council meeting. RCWD relocation work expected to start at end of October 2011
|
Old Town Gymnasium
This projects involves the design of the approximately 9,000 square foot gymnasium adjacent the Boys & Girls Club on Pujol Street. The City Council adopted the Mitigated Negative Declaration (MND) and authorized staff to solicit construction bids for Phase I at the 06/14/11 meeting. Consultant is finalizing the plans.
|
Santa Gertrudis Creek Pedestrian/Bicycle Trail Extension and Interconnect
The project will provide a Class I bicycle trail that connects the existing Santa Gertrudis Creek Pedestrian/Bicycle Trail at Ynez Road to the Murrieta Creek Multi-Purpose Trail at Diaz Road. The alignment study has been completed. Extension of time for the Bicycle Transportation Account funds was approved on 05/01/09. The consultant is working on 90% plans, specifications and estimate.
|
Nicolas Valley - Assessment District (Liefer Road)
This project will study assessment district feasibility and formation, including completing the street and minor storm drain improvements on the unimproved portions of certain streets within Nicolas Valley (Liefer Road) area. Consultant is finalizing 100% plans for signature.
|
I-15 / SR-79S Ultimate Interchange
95% PS&E (2nd Submittal) - Caltrans comments received.
|
Pavement Rehabilitation Program
These rehabilitation projects will rehabilitate portions of Winchester, Rancho California, Ynez, Margarita Road and Rancho Vista Road's. City has received final plans for Margarita Road, Project 1, Winchester Road and Rancho Vista Road. The consultant continues to finalize the design for the rest of the projects.
|
French Valley Parkway / Interstate-15 OverCrossing and Interchange Improvements - Phase II
The City Council approved the design agreement with TY Lin at the 09/13/2011 City Council meeting.
|
Library Parking Expansion
This project will add on-street parking adjacent to the Temecula Library and Fire Station #84 on Pauba Road. The Consultant is preparing the Water Quality Management Plan (WQMP). The City received the 100% plans.
|
Projects Being Designed By StaffCitywide Storm Drain Improvements - Calle Fiesta
This project consists of extending an existing City-maintained storm drain line an additional 200 feet to eliminate slope erosion at the current storm drain discharge point. The necessary drainage easement for future City access and maintenance of the new pipe will be presented to the City Council for approval at the 09/27/11 City Council meeting. The project will be bid for construction shortly.
|