| |
Projects Under ConstructionRoripaugh Ranch Fire Station
The majority of work was completed by April of 2006. The remaining work will be completed when the mainline utilities are installed, which the City is undertaking - estimated start in March of 2010. A fire engine/truck venting system (requested/added on 2/06) will be installed when the Contractor re-mobilizes, this cost is also included in the approved change order total.
|
City Property at Diaz Road and Dendy Parkway (Northwest RDA Property) - Rough Grading
This project provided for the rough grading of the vacant City property at Diaz Road and Dendy Parkway. All work was completed on March 28, 2007. Site restoration, including hydroseeding, was completed in December of 2008. A notice of completion was approved by the City Council at the 1/13/09 meeting. Ongoing maintenance expenses will be incurred for NPDES measures until such time the property is developed. Minor BMP improvements were completed in late November of 2009.
|
Old Town Infrastructure Project -Town Square and Mercedes & Main Street
This project involves construction of the Town Square and street improvements on Mercedes & Main Streets. The project was awarded on March 18, 2008. All storm drain, sewer, and water improvements are complete and all the roadways are paved. Work near completion in the Town Square and the Fountain is fully functional. Various specialty items and added work extended the completion date through December 2009.
|
Pechanga Parkway Phase II Street Improvements from Temecula Parkway to City Limits @ Pechanga Rd.
This project widens Pechanga Pkwy to its ultimate width from Temecula Pkwy to Pechanga Rd. The contractor has essentially completed the improvements including the "dual right turn lanes" work. The remaining work includes punch list items to include ridability and EMWD manhole adjustments. There is a claim to the City from EMWD regarding damages to their facilities that the contractor has allegedly caused. The project is substantially complete, as of August 2009.
|
Old Town Infrastructure Projects
- Parking Structure & Office/Retail Frontage
This project includes the site grading and retaining walls for the Civic Center & the Parking Structure site as well as construction of a parking structure, including office frontage shell space. Work is ongoing on exterior facade, landscaping and hardscapes. The structure is anticipated to open near the end of February 2010.
|
Ronald Reagan Sports Park Channel Silt Removal & Desiltation Pond
This project includes restoring the Best Management Practices (BMP) of the Stormwater Pollution Prevention Plan (SWPPP), the Water Quality Management Plan (WQMP) and the requirements of RWQCB by desilting the basin located near the Sports Park. 401 Certification, Streambed Alteration Agreement, and Nationwide Permits have been acquired. Bids were opened on 08/26/08 and awarded on 12/08/09. Notice to Proceed effective 01/01/10. Construction has begun. Contractor is working on the dewatering and vegetation removal.
|
Old Town Civic Center
This project will construct the Old Town Civic Center. City Council awarded the contract to Edge Development, Inc. on 09/09/08. Edge began work on 4/8/09. Work is ongoing on steel stud framing, and rough in of mechanical, electrical and plumbing.
|
Temecula Community Center Expansion
Work began on January 13, 2009. The building is complete SAFE has moved in. Exterior punchlist is pending. The Escallier house and barn have been fumigated for termites. Dry rot & termite infested wood has been removed and replaced. Staff has reviewed 100% Plans and edits are required; the consultant agreement amendment to perform this additional work was approved by City Council on 11/10/09. Staff is reviewing the final plans and specifications after incorporating Building & Safety corrections. Project bidding is scheduled for the beginning of February.
|
Redhawk Park Improvements
This project will add amenities, which include ADA accessible parking, a restroom, a half-court basketball court, and permanent dog park at Redhawk Community Park. As part of this project, a seatwall will be installed at Sunset Park. The Notice To Proceed was issued 12/21/09. Construction activities began in January 2010. Completion is anticipated in June 2010.
|
De Portola Road Pavement Rehabilitation Project (from Jedediah Smith to Margarita)
This project involves rehabilitating De Portola Rd pavement from Jedediah Smith to Margarita Rd. This is a federally funded project. Construction began the week of 3/16/09. Catch basin filter insert installation is the only remaining item of contract work. Change order work involving modification of an existing drainage structure is complete; hydroseeding the drainage channel took place on 1/15/10. Specified catch basin filters have been found to be incompatible, and will need to be re-specified/re-ordered. Final installation to take place before the end of January.
|
Pavement Rehabilitation Rancho California Road (Ynez to East City Limit) - STPL Project
This project will rehabilitate Rancho California Road from Ynez Road to the City limits on the east. Construction began on June 3, 2009 and is anticipated to be completed by the end of January 2010. The contractor is working in the final section between Meadows Parkway and Butterfield Stage Road.
|
Winchester Road / State Route 79 North - North Corridor Beautification
This federally funded project will design and construct landscaping and irrigation enhancements to the existing raised medians along Winchester Road between Ynez Road and the easterly City limits. The City received construction authorization from Caltrans. The City Council approved the plans and specifications at the 10/27/09 meeting. Bids were opened on 11/30/09. This project was awarded at the 12/08/09 City Council meeting to Belaire-West Landscape. The award amount was $920,027. Construction is scheduled to start some time after March 1, 2010.
|
Traffic Signal Interconnect Equipment Installation
This project will install traffic signal interconnect equipment on Margarita Road, from Rancho California Road to Pio Pico Road. The Notice to Proceed letter was given to the contractor to start on November 23, 2009 for a 50-work day duration. Construction continues. Project is scheduled to end in Mid February.
|
Projects Being Advertised for BidsCitywide Slurry Seal Project FY 2009-2010
This project will slurry seal local streets within the Roripaugh Hills Estates, Campus Verdes and Nicholas Valley Areas. Proposition 1B funds will be used to fund this project. Project is scheduled for a March 2, 2010 bid opening date.
|
Projects Being Designed By ConsultantsRe-Stripe Route 79 South to 8 lanes from Pechanga Parkway to I-15
This project will provide four lanes in each direction on Temecula Parkway (formerly State Route 79 South) from I-15 to Pechanga Parkway. The City is working to meet Caltrans requirements to do the striping.
|
Pechanga Parkway Storm Drain Improvements - Environmental Mitigation
This project includes construction of new wetlands for the Wolf Valley Creek Channel Improvements-Stage I. The wetlands will be created through construction of new landscape/irrigation systems. The site is located along the north bank of Temecula Creek (within flood-plain/way areas). The environmental regulatory agencies have approved this new mitigation area. Mylars are ready for signature. Offers for purchase of the properties were made and City Council adopted a Resolution of Necessity to acquire the property on 11/25/08. The proposed improvements can't be implemented until the City obtains possession of the properties. The California Department of Fish & Game will have to sign off on this acquisition since they have jurisdiction over land the City will use for access.
|
Murrieta Creek Bridge and Overland Drive Extension from Commerce Center to Diaz Rd
The project includes the extension of Overland Drive from Commerce Center Drive to Diaz Road with a bridge over Murrieta Creek. Coordination with RCFC & WCD, U.S. Army Corps of Engineers and the state environmental regulatory agencies is required. The 100% completion plans were submitted on November 16, 2009. They were returned to the consultant for final red-line correction with final submittal in January. Extension of time is going to be granted to consultant until March 31, 2010 to finalize plans.
|
Main Street Bridge Over Murrieta Creek (Replacement)
This project will replace the existing Main Street Bridge over Murrieta Creek. Design consultant Simon Wong Engineering (SWE) and the City are continuing to pursue environmental permitting and coordination issues associated with pursuing the bridge replacement as a project separate from the Army Corps of Engineer's Murrieta Creek Improvement project. Comments on the environmental technical reports were received from Caltrans on 4/28/09, and are being addressed by the consultant. The draft 100% PS&E package was received from the design consultant on 2/17/09, and staff review is complete. Comments on draft 100% plans resubmitted to design consultant 8/31/09. An inter-agency meeting was held on 9/16/09 to determine mitigation requirements for this project. The outcome of this meeting was that the City will be required to mitigate for temporary vegetation loss incurred during construction; all other mitigation will be included in the USACOE overall Murrieta Creek flood control project. The environmental submittal/review process will now move forward accordingly. The mitigation plan for temporary impacts was delivered to the City for comment on 1/15/10, and returned to the design consultant for finalization on 1/21/10. Resubmittal of environmental technical reports to Caltrans anticipated the week of 1/25/10.
|
Pedestrian/Bicycle Bridge Over Santa Gertrudis Creek
This project includes the construction of an approx. 150' ped/bike bridge over Santa Gertrudis Creek near Chaparral H.S. This is a federally funded project, which will involve a NEPA document. The approved Preliminary Environmental Study (PES) form was received from Caltrans on 12/03/08; technical reports were submitted to Caltrans on 5/13/09. Staff comments on draft 100% plans were returned to consultant on 5/27/09. Comments on environmental technical reports received from Caltrans in June, and have been addressed by City staff and consultants. Comments from Caltrans on second submittal of environmental technical reports received from Caltrans on 1/20/10, and are being addressed by the design consultant and City staff.
|
Western Bypass Bridge Over Murrieta Creek
This project involves the design, environmental clearance, and construction of a new bridge over Murrieta Creek at the westerly terminus of Western Bypass and an extension of Pujol Street to the new structure. Once constructed, this will serve as the southerly connection of the Western Bypass Corridor. Design is underway. Geotechnical investigations have been initiated and 90% Plans and Specs are being reviewed. The Mitigated Negative Declaration was adopted. Applications to the various environmental agencies have been submitted.
|
Temecula Park and Ride (79 South)
This project will design and construct a park and ride facility on Temecula Parkway (formerly 79 South) at La Paz. The 70% design drawings were returned to AAE for revision and resubmittal. City and consultant are discussing some of the comments. The consultant is working to finalize the plans. 90% submittal is expected in February.
|
Pechanga Pkwy-Dual Right Turn Lanes from
Temecula Parkway (SR 79S)
This project included the design and construction of 2 right-turn lanes on eastbound Temecula Pkwy to southbound Pechanga Pkwy. The Pechanga Pkwy Ph II Street Improvements' contractor has completed this work, as a change order to their contract.
|
French Valley Parkway / Interstate 15 Over-Crossing and Interchange Improvements - Phase 1 (PS&E)
A southbound off-Ramp to Jefferson, an auxiliary lane, and widening the bridge over Santa Gertrudis Creek at the Winchester southbound off-ramp are the components of Phase 1. City continued the design work. Status is as follows:
> PS&E - City is preparing 95% Plans, Specifications, and Estimate.
> Right of Way - Establishing limits of dedication.
> Declaration of Units - Caltrans Approved Metric Exception for this phase.
> Utilities - Pothole of existing utilities within APE are complete.
> Conceptual Landscape/Aesthetics - Concept was selected, with Murrieta, Caltrans, and IBC concurrence. Selection was incorporated into Draft Structures PS&E submittal.
Other:
> Maintenance Agreement - City preparing exhibit for first draft.
|
Old Town Gymnasium
This projects involves the design of the approximately 9,000 square foot gymnasium adjacent the Boys & Girls Club on Pujol Street. WLC is still working on design scenarios with Boys and Girls Club Staff. The land is to be utilized as staging area for the Murrieta Creek Improvements project and it will need to be acquired from Riverside County Flood Control (RCFC) for the current design. A time line was established by TCSD for the design and environmental work. The City Council subcommittee gave staff the go ahead to proceed with the construction drawings on 01-26-2010. This work is underway. Construction is projected to start in Spring 2011.
|
Santa Gertrudis Creek Pedestrian/Bicycle Trail Extension and Interconnect
The project will provide a Class I bicycle trail that connects the existing Santa Gertrudis Creek Pedestrian/Bicycle Trail at Ynez Road to the Murrieta Creek Multi-Purpose Trail at Diaz Road. The City Council approved an agreement with Hall & Foreman at the 11/25/08 meeting. The kick off meeting was held on 01/08/09. The alignment study has been completed. Extension of time for the Bicycle Transportation Account funds was approved on 05/01/09. The consultant has submitted 70% plans, specifications and estimate.
|
Nicolas Valley - Assessment District (Liefer Road)
This project will study assessment district feasibility and formation, including completing the street and minor storm drain improvements on the unimproved portions of certain streets within Nicolas Valley (Liefer Road) area. The City Council approved an agreement for the street improvement design with David Evans and Associates at the 10/28/08 City Council Meeting. The kick off meeting for the design of the street improvements was held on 12/17/08. Consultant is preparing 90% plans, specifications and estimate.
|
Roripaugh Ranch Street Improvements - Phase I
Phase I includes the design & construction of Butterfield Stage Road (BSR) from Murrieta Hot Springs Road (MHSR) to Calle Chapos, a portion of MHSR, Calle Chapos, South Loop Rd and making the Fire Station functional. Liens and settlements have been resolved. On 11/24/09, David Evans and Associates' (DEA) was awarded a contract to complete the design. On 1/12/10 Hirsh & Associates, Inc. was awarded a contract to complete the landscape design. Staff is working on the Bid Package. The City Attorney is to review the impacts associated with Paradigm's involvement in regards to the FDIC's new involvement.
|
Traffic Signal Installation - Citywide
This project will install traffic signals at two intersections; Meadows Parkway at Pauba Road and Rancho California Road at Yukon Road. Notice To Proceed was issued 12/21/09 for design activities. Completion of Plans and Specifications is anticipated in June 2010.
|
I-15 / SR-79S Ultimate Interchange
The City's consultant is preparing 65% PS&E package for Caltrans review in January 2010.
|
Projects Being Designed By StaffLong Canyon Detention Basin - Access Road
Plans and specifications are 90% complete. City is seeking FEMA funds to remove excess silt deposited within the basin before constructing the access road. Project is on hold until FEMA determination is finalized.
|
Road and Storm Drain Repair at Rancho California Road
Staff is in the data-gathering stage to determine the best method of pipe/roadway repair. A video inspection of the pipe's interior was performed on 11/4/09, and revealed evidence of possible corrosion. A physical inspection of the pipes' interior was performed on 12/17/09 with the assistance of a local pipeline contractor which revealed that the pipe wall was essentially in good condition, with some areas of rust in the pipe invert. The approach from this point may take the form of rust removal and application of a protective coating to extend the life of the pipe; no major repair is anticipated.
|
Citywide Storm Drain Improvements - Rancho California Rd at Vincent Moraga Dr
Staff is modifying existing storm drain plans that were a part of the Diaz Road Realignment project (Phase II), but were never constructed due to a conflict with Rancho California Water District (RCWD) facilities. Draft construction plans have been completed, and a Notice to Relocate was issued to RCWD. RCWD has responded with a request to incorporate the facility relocation into the City construction contract, and has provided a relocation plan to the City. RCWD relocation plan currently being incorporated into City construction documents; bid package expected to be complete mid-January. Authorization to bid is being requested from City Council at the January 26, 2010 City Council Meeting.
|
Road Reconstruction at Jedediah Smith Road
Staff is coordinating with a consultant to develop a bid package based on ARAM (Asphalt Rubber Aggregate Membrane) technology. Bid package anticipated to be complete mid-January; authorization to bid is to be requested from City Council in February.
|
Citywide Slurry Seal Project FY 2009-2010
|
Citywide Concrete Repairs FY 2009-10
|
Projects in the Planning StageFrench Valley Parkway / Interstate 15 Over-Crossing and Interchange Improvements (PA & ED)
This project will construct an interchange between Winchester Road Interchange and the I-15/I-215 split. City continued development of the Project Report and Environmental Document. Status is as follows:
> Draft Project Report - Approved June 2006.
> Project Report - City preparing final report.
> Draft Environmental Document - Approved April 2009.
> New Connection Report (NCR) - Letter of Acceptability received in July 2008.
> Traffic Operations Analysis - Approved 02/05/08.
> Exception to 20-yr Traffic Design - Approved 12/17/07.
> Stormwater Data Report - Approved 01/05/10.
> Mandatory Design Exceptions - Approved 07/18/06.
> Advisory Design Exceptions - Approved 07/18/06.
> Exception to Ramp Metering Policy - Approved 07/05/06.
> Geometric Approval Drawings - Approved 07/18/06.
> Revised Geometric Approval Drawings - Approved 01/11/08.
> Storm Drain Study - Approved 03/21/08.
> Floodplain and Scour Analysis Report - Approved Oct 2008.
> Final Environmental Document - City preparing final report.
Other:
> Declaration of Units - Request for Metric Exception denied by Caltrans.
> Freeway Agreements - Execution pending approval of the Project Report.
> Risk Management Plan - Updating as necessary.
> Project Charter - 1st draft is under Caltrans review.
> Maintenance Agreement - Preparing 1st submittal for Caltrans review.
> Financial Plan - Updating as necessary.
|