Last Updated October 28, 2008
French Valley Parkway Phase 1 - Southbound Off-Ramp to Jefferson, Auxiliary Lane, and Widening the Bridge over Santa Gertrudis Creek at the Winchester Southbound Off-ramp
A southbound off-ramp to Jefferson, an auxiliary lane, and widening the bridge over Santa Gertrudis Creek at the Winchester southbound off-ramp are the components of Phase 1. Status is as follows:
Ø PS&E – City is preparing 95% plans (retaining walls and landscape/irrigation).
Ø Type Selection for Retaining Walls - Approved November 2007.
Ø 2nd Intermediate PS&E for Retaining Walls - Under Caltrans review.
Ø Right of Way - Establishing limits of dedication. Discussions are continuing with owners of affected parcels within Phase 1 work.
Ø Declaration of Units – Caltrans Approved Metric Exception for this phase.
Ø Utilities - Updated pothole plans have been reviewed by Caltrans. Encroachment permits are being sought.
Ø Conceptual Landscape/Aesthetics - Concept was selected, with Murrieta, Caltrans, and IBC concurrence. Selection was incorporated into Draft Structures PS&E submittal.
Ø Maintenance Agreement - City preparing exhibit for the first draft. French Valley Parkway Overcrossing and Interchange, Project Report (PR), Plans Specifications, and Estimate (PS&E) Preparation
This project will construct an interchange between Winchester Road Interchange and the I-15/I-215 split. City continued development of the Project Report and Environmental Document. Current status is as follows:
Ø Draft Project Report - Approved June 2006.
Ø Project Report - Final preparation pending approval of Environmental Doc.
Ø Draft Environmental Document - City revising per Caltrans comments.
Ø New Connection Report (NCR) - Letter of Acceptability received in July 2008.
Ø Traffic Operations Analysis - Approved 02/05/08.
Ø Exception to 20-yr Traffic Design - Approved 12/17/07.
Ø Stormwater Data Report - City revising per Caltrans comments.
Ø Mandatory Design Exceptions - Approved 07/18/06.
Ø Advisory Design Exceptions - Approved 07/18/06.
Ø Exception to Ramp Metering Policy - Approved 07/05/06.
Ø Geometric Approval Drawings - Approved 07/18/06.
Ø Revised Geometric Approval Drawings - Approved 01/11/08.
Ø Storm Drain Study - Approved 03/21/08.
Ø Floodplain and Scour Analysis Report - Under Caltrans review.
Ø Declaration of Units - Request for Metric Exception denied by Caltrans.
Ø Freeway Agreements - Revised exhibits under Caltrans review.
Ø Risk Management Plan - Updating as necessary.
Ø Project Charter - 1st draft is under Caltrans review.
Ø Maintenance Agmt - Preparing 1st submittal for Caltrans review.
Ø Financial Plan - Preparing 2nd submittal for Caltrans review.
|